Lift Station Upgrade 2018

Trinity Bay North, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$103,880
Federal share33%

of $317.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
20192020
Built

Approved 16 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Trinity Bay North
Construction start
Jul 15, 2019(actual)
Construction end
Jun 5, 2020(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Aug 1, 2019
  • Construction end6 months lateforecast Dec 1, 2019