Water System Upgrade, Phase IV
Trinity Bay North, Newfoundland and Labrador
Federal contribution
$317,952
Federal share33%
of $955.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Trinity Bay North
- Construction start
- Aug 11, 2010(actual)
- Construction end
- Mar 15, 2017(actual)
Against the original forecast
- Construction start10 months lateforecast Oct 1, 2009
- Construction end11 months lateforecast Mar 31, 2016
Also in Trinity Bay North
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26740 in the federal list. How to read these figures.