Schedule

Announced and approvedJul 15, 2008
2009
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
May 20, 2009(actual)
Construction end
Jun 5, 2009(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2009
  • Construction end22 months earlyforecast Mar 31, 2011

Also in Chester