Back to projects

Western Shore Wastewater Treatment Plant Improvements

Chester, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$799,015
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
May 22, 2018(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Mar 31, 2018

Also in Chester