Mill Cove wastewater treatment plant replacement
Federal contribution
$694,316
Federal share48%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of the District of Chester
- Construction start
- May 3, 2017(actual)
- Construction end
- Mar 15, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2017
- Construction end13 months earlyforecast Mar 31, 2019
Also in Chester