Back to projects

Mill Cove wastewater treatment plant replacement

Chester, Nova Scotia

completeWastewaterCWWF
Federal contribution
$694,316
Federal share48%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 3, 2017(actual)
Construction end
Mar 15, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 1, 2017
  • Construction end13 months earlyforecast Mar 31, 2019

Also in Chester

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47202 in the federal list. How to read these figures.