Village of Chester Wastewater System Renewal Project - Phase 1

Chester, Nova Scotia

underwayWastewaterGIS
Federal contribution
$3.3M
$3,336,000
Federal share18%

of $18.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2023
today
20232024202520262027
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jan 16, 2024(actual)
Construction end
Aug 31, 2027(forecast)

Against the original forecast

  • Construction start2 months earlyforecast Apr 1, 2024

Also in Chester

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65824 in the federal list. How to read these figures.