Tancook Island Ferry Replacement

Chester, Nova Scotia

underwayMarineRNIS
Federal contribution
$5.2M
$5,229,751
Federal share43%

of $12.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 4, 2020
today
20192021202320252027
BuiltForecast

Approved 20 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Province of Nova Scotia
Construction start
Feb 21, 2021(actual)
Construction end
Sep 25, 2026(forecast)

Against the original forecast

  • Construction start7 weeks lateforecast Jan 4, 2021