Municipality of Chester AT Modal Shifts & New Connections
Federal contribution
$4.5M
$4,485,913
Federal share22%
of $20.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2026
today
202220232024202520262027
BuiltForecast
Approved 4.2 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the District of Chester
- Construction start
- Oct 11, 2022(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start3 months lateforecast Jul 4, 2022
Also in Chester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60696 in the federal list. How to read these figures.