Back to projects

Starrs Road Storm Sewer

Yarmouth, Nova Scotia

completeWastewaterCC
Federal contribution
$196,700
Federal share33%

of $590.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2008
2009
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Yarmouth
Construction start
Mar 12, 2009(actual)
Construction end
Jun 26, 2009(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast May 1, 2009
  • Construction end21 months earlyforecast Mar 31, 2011

Also in Yarmouth