Starrs Road Storm Sewer
Federal contribution
$196,700
Federal share33%
of $590.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2008
2009
Built
Approved 8 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Yarmouth
- Construction start
- Mar 12, 2009(actual)
- Construction end
- Jun 26, 2009(actual)
Against the original forecast
- Construction start7 weeks earlyforecast May 1, 2009
- Construction end21 months earlyforecast Mar 31, 2011
Also in Yarmouth