Canim Lake Water System

Williams Lake, British Columbia

completeDrinking WaterCC
Federal contribution
$98,707
Federal share19%

of $517.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 23, 2009
20092010201120122013
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 15, 2009(actual)
Construction end
May 31, 2013(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 5, 2009
  • Construction end6 months lateforecast Nov 30, 2012