Canim Lake Water System
Williams Lake, British Columbia
Federal contribution
$98,707
Federal share19%
of $517.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 23, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Regional District of Cariboo
- Construction start
- Jul 15, 2009(actual)
- Construction end
- May 31, 2013(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 5, 2009
- Construction end6 months lateforecast Nov 30, 2012
Also in Williams Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22652 in the federal list. How to read these figures.