Mackenzie Avenue Resurfacing

Williams Lake, British Columbia

completeHighways and RoadsISF
Federal contribution
$3.5M
$3,496,756
Federal share33%

of $10.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Williams Lake
Construction start
Jun 1, 2010(actual)
Construction end
Sep 17, 2011(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Aug 31, 2011