Williams Lake Air Tanker Base
Williams Lake, British Columbia
Federal contribution
$398,619
Federal share28%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Jul 30, 2011(actual)
Also in Williams Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39080 in the federal list. How to read these figures.