River Valley Trunk Sewer Upgrades
Williams Lake, British Columbia
Federal contribution
$1.3M
$1,340,063
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2015
201620172018
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Williams Lake
- Construction start
- Aug 18, 2016(actual)
- Construction end
- Dec 11, 2017(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 29, 2017