Williams Lake - Pressure Media Filtration Water Treatment Plant
Williams Lake, British Columbia
Federal contribution
$9.7M
$9,726,750
Federal share40%
of $24.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 27, 2023
today
20242025202620272028
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Williams Lake
- Construction start
- Oct 1, 2026(forecast)
- Construction end
- Mar 31, 2028(forecast)