T’exelcemc - Williams Lake Indian Band Administrative & Community Building

Williams Lake, British Columbia

completeCultureCCRIS
Federal contribution
$1.5M
$1,493,190
Federal share75%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2019
20202021
Built
Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
T'exelcemc, First Nation
Construction start
Apr 6, 2020(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start12 months earlyforecast Apr 1, 2021
  • Construction end2 months earlyforecast Dec 1, 2021

Also in Williams Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54723 in the federal list. How to read these figures.