Improvements to the lift station on De la Rive Street (22-06)

Tracadie-Sheila, New Brunswick

completeWastewaterCC Top Up
Federal contribution
$91,530
Federal share33%

of $274.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2009
2010
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Tracadie-Sheila
Construction start
May 17, 2010(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 20, 2009
  • Construction end2 months earlyforecast Dec 31, 2010