Wastewater Collection System Upgrade

Bathurst, New Brunswick

completeWastewaterCC
Federal contribution
$400,356
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Bathurst
Construction start
Jun 21, 2010(actual)
Construction end
Nov 25, 2010(actual)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2009
  • Construction end11 months lateforecast Dec 11, 2009

Also in Bathurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23069 in the federal list. How to read these figures.