Wastewater Collection System Upgrade
Federal contribution
$400,356
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2009
2010
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Bathurst
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Nov 25, 2010(actual)
Against the original forecast
- Construction start13 months lateforecast Jun 1, 2009
- Construction end11 months lateforecast Dec 11, 2009
Also in Bathurst
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23069 in the federal list. How to read these figures.