Hydrological Evaluation and Cleaning of Clear Well
Federal contribution
$23,467
Federal share33%
of $70.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Val Rita-Harty
- Construction start
- May 14, 2009(actual)
- Construction end
- Sep 30, 2009(actual)
Also in Val Rita-Harty