Back to projects

Renovation and Refurbishment of the Drinking Water Treatment Facility in the Village of Val Rita

Val Rita-Harty, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.0M
$1,978,237
Federal share40%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023202420252026
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Val Rita-Harty
Construction start
Apr 3, 2023(actual)
Construction end
Mar 31, 2026(forecast)

Also in Val Rita-Harty

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62824 in the federal list. How to read these figures.