Critical Municipal Building Repairs and Upgrades
Federal contribution
$67,156
Federal share80%
of $83.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Val Rita-Harty
- Construction start
- Jul 5, 2021(actual)
- Construction end
- May 3, 2022(actual)
Against the original forecast
- Construction end7 weeks lateforecast Mar 18, 2022
Also in Val Rita-Harty
- Renovation and Refurbishment of the Drinking Water Treatment Facility in the Village of Val Rita$2.0M
- Rehabilitation of the Val Rita-Harty community centre$98.6K
- Municipal Chalet$30.1K
- Replace the power generator at the water treatment plant$27.5K
- Hydrological Evaluation and Cleaning of Clear Well$23.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59361 in the federal list. How to read these figures.