Rehabilitation of the Val Rita-Harty community centre
Federal contribution
$98,620
Federal share40%
of $246.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20212022
Built
Approved 6 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Val Rita-Harty
- Construction start
- Jan 4, 2022(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction end8 weeks lateforecast May 31, 2022