Back to projects

Municipal Chalet

Val Rita-Harty, Ontario

completeTourismISF
Federal contribution
$30,145
Federal share33%

of $90.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Val Rita-Harty
Construction start
Sep 17, 2009(actual)
Construction end
Dec 22, 2009(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Nov 30, 2009

Also in Val Rita-Harty

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29978 in the federal list. How to read these figures.