Construction of a Multi-Use Health and Wellness Recreation Centre
Federal contribution
$6.9M
$6,866,667
Federal share33%
of $20.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Port Colborne
- Construction start
- Apr 1, 2011(actual)
- Construction end
- Feb 15, 2013(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 1, 2012
Also in Port Colborne
- Seaway Wastewater Treatment Plant Expansion$7.2M
- Watermain Replacement in Port Colborne$2.0M
- Highway 140 - Highway 3 to Niagara Road 23 in Port Colborne$1.5M
- Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed$361.7K
- Port Cares Reach Out Centre Renovations$335.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23191 in the federal list. How to read these figures.