Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed
Federal contribution
$361,655
Federal share49%
of $734.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Port Colborne
- Construction start
- Jun 27, 2019(actual)
- Construction end
- Sep 27, 2019(actual)
Against the original forecast
- Construction start2.2 years lateforecast May 1, 2017
- Construction end3 months earlyforecast Dec 20, 2019