Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed

Port Colborne, Ontario

completeDrinking WaterCWWF
Federal contribution
$361,655
Federal share49%

of $734.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Port Colborne
Construction start
Jun 27, 2019(actual)
Construction end
Sep 27, 2019(actual)

Against the original forecast

  • Construction start2.2 years lateforecast May 1, 2017
  • Construction end3 months earlyforecast Dec 20, 2019

Also in Port Colborne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48568 in the federal list. How to read these figures.