Back to projects

Seaway Wastewater Treatment Plant Expansion

Port Colborne, Ontario

completeWastewaterISF
Federal contribution
$7.2M
$7,182,492
Federal share33%

of $22.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 2, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Port Colborne

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32338 in the federal list. How to read these figures.