Watermain Replacement in Port Colborne
Federal contribution
$2.0M
$1,999,200
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023202420252026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Port Colborne
- Construction start
- Oct 22, 2024(actual)
- Construction end
- Jul 30, 2026(forecast)
Against the original forecast
- Construction start3 weeks lateforecast Sep 30, 2024
Also in Port Colborne
- Seaway Wastewater Treatment Plant Expansion$7.2M
- Construction of a Multi-Use Health and Wellness Recreation Centre$6.9M
- Highway 140 - Highway 3 to Niagara Road 23 in Port Colborne$1.5M
- Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed$361.7K
- Port Cares Reach Out Centre Renovations$335.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62891 in the federal list. How to read these figures.