Port Cares Reach Out Centre Renovations
Federal contribution
$335,000
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Port Colborne Association for Resource Extension
- Construction start
- Nov 17, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 15, 2010
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Port Colborne
- Seaway Wastewater Treatment Plant Expansion$7.2M
- Construction of a Multi-Use Health and Wellness Recreation Centre$6.9M
- Watermain Replacement in Port Colborne$2.0M
- Highway 140 - Highway 3 to Niagara Road 23 in Port Colborne$1.5M
- Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed$361.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33852 in the federal list. How to read these figures.