Upgrading Highway 11 outside Fort Frances

Fort Frances, Ontario

completeHighways and RoadsCC
Federal contribution
$10,000
Federal share33%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 14, 2010(actual)
Construction end
Sep 27, 2010(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 13, 2009
  • Construction end4 weeks lateforecast Aug 31, 2010

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24772 in the federal list. How to read these figures.