Upgrading of Japada Road

Fort Frances, Ontario

completeHighways and RoadsCC
Federal contribution
$27,061
Federal share45%

of $60.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Jul 13, 2009(actual)
Construction end
Jun 24, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 20, 2009
  • Construction end7 weeks earlyforecast Aug 13, 2010

Also in Fort Frances

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24833 in the federal list. How to read these figures.