North County Potable Water Co-op

Lethbridge, Alberta

completeDrinking WaterCC
Federal contribution
$3.0M
$3,000,000
Federal share32%

of $9.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 30, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Lethbridge No. 26
Construction start
Mar 31, 2009(actual)
Construction end
Aug 31, 2012(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 1, 2009
  • Construction end23 months lateforecast Sep 30, 2010