Phase 1 - West Lethbridge Recreation Campus
Federal contribution
$10.0M
$10,000,000
Federal share29%
of $34.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 15, 2013
20122013201420152016
Built
Approved 19 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Lethbridge
- Construction start
- Oct 21, 2013(actual)
- Construction end
- Feb 29, 2016(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2013
- Construction end4 months earlyforecast Jun 30, 2016
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41373 in the federal list. How to read these figures.