Scenic Drive North
Federal contribution
$3.0M
$3,000,000
Federal share16%
of $18.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Lethbridge
- Construction start
- Jun 25, 2012(actual)
- Construction end
- Jun 30, 2014(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 1, 2011
- Construction end22 months lateforecast Sep 1, 2012
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25291 in the federal list. How to read these figures.