Lethbridge Broadband Fibre
Federal contribution
$5.6M
$5,600,977
Federal share79%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
today
2021202320252027
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Lethbridge
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Mar 31, 2028(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Jul 5, 2021
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58747 in the federal list. How to read these figures.