Community Performing Arts Centre

Lethbridge, Alberta

completeCultureCC
Federal contribution
$3.0M
$3,000,000
Federal share22%

of $13.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Lethbridge
Construction start
Jun 1, 2011(actual)
Construction end
Oct 16, 2013(actual)

Against the original forecast

  • Construction start13 months lateforecast May 1, 2010
  • Construction end2 years lateforecast Sep 30, 2011