Community Performing Arts Centre
Federal contribution
$3.0M
$3,000,000
Federal share22%
of $13.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Lethbridge
- Construction start
- Jun 1, 2011(actual)
- Construction end
- Oct 16, 2013(actual)
Against the original forecast
- Construction start13 months lateforecast May 1, 2010
- Construction end2 years lateforecast Sep 30, 2011
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25183 in the federal list. How to read these figures.