Infrastructure Upgrading

Bashaw, Alberta

completeHighways and RoadsCC
Federal contribution
$594,266
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 30, 2009
200920102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Bashaw
Construction start
Aug 31, 2009(actual)
Construction end
May 15, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 3, 2009
  • Construction end7 months lateforecast Sep 30, 2010

Also in Bashaw

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24899 in the federal list. How to read these figures.