Regional Water Pipeline - Mirror to Bashaw
Federal contribution
$3.5M
$3,500,000
Federal share50%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Highway 12/21 Regional Water Services Commission
- Construction start
- Feb 14, 2017(actual)
- Construction end
- May 23, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Nov 1, 2016
- Construction end3 weeks lateforecast Apr 30, 2019
Also in Bashaw
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47599 in the federal list. How to read these figures.