Regional Water Pipeline - Mirror to Bashaw

Bashaw, Alberta

completeDrinking WaterCWWF
Federal contribution
$3.5M
$3,500,000
Federal share50%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Feb 14, 2017(actual)
Construction end
May 23, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Nov 1, 2016
  • Construction end3 weeks lateforecast Apr 30, 2019