Resurfacing Highway 21 from South Bashaw to Highway 53

Bashaw, Alberta

completeHighways and RoadsISF
Federal contribution
$2.5M
$2,546,278
Federal share50%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
May 7, 2010(actual)
Construction end
Aug 18, 2010(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2011