Watermain Replacement and Insulation

Bashaw, Alberta

completeDrinking WaterISF
Federal contribution
$211,917
Federal share33%

of $635.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Bashaw
Construction start
Jun 14, 2010(actual)
Construction end
Oct 28, 2011(actual)