Bashaw Lagoon Upgrade

Bashaw, Alberta

completeWastewaterGIS
Federal contribution
$286,090
Federal share40%

of $715.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2020
2021
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Bashaw
Construction start
Jun 1, 2021(actual)
Construction end
Sep 16, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2021
  • Construction end2 weeks earlyforecast Sep 30, 2021

Also in Bashaw

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56659 in the federal list. How to read these figures.