Turin Wastewater System

Lethbridge, Alberta

completeWastewaterCC Top Up
Federal contribution
$790,147
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
County of Lethbridge No. 26
Construction start
May 1, 2010(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Lethbridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25884 in the federal list. How to read these figures.