Turin Wastewater System
Federal contribution
$790,147
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Lethbridge No. 26
- Construction start
- May 1, 2010(actual)
- Construction end
- Oct 28, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Jul 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25884 in the federal list. How to read these figures.