Mountain Meadows Production Well Facility
Federal contribution
$295,000
Federal share33%
of $885.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Lethbridge No. 26
- Construction start
- Jul 12, 2011(actual)
- Construction end
- Mar 20, 2013(actual)
Against the original forecast
- Construction start21 months lateforecast Oct 1, 2009
- Construction end2.6 years lateforecast Aug 1, 2010
Also in Lethbridge