Cape Forchu Lightstation

Yarmouth, Nova Scotia

completeCultureCC Top Up
Federal contribution
$281,552
Federal share33%

of $844.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jan 6, 2010(actual)
Construction end
Mar 24, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Jun 1, 2009
  • Construction end11 months lateforecast May 1, 2010

Also in Yarmouth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26378 in the federal list. How to read these figures.