Cape Forchu Lightstation
Federal contribution
$281,552
Federal share33%
of $844.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of the District of Yarmouth
- Construction start
- Jan 6, 2010(actual)
- Construction end
- Mar 24, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Jun 1, 2009
- Construction end11 months lateforecast May 1, 2010
Also in Yarmouth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26378 in the federal list. How to read these figures.