Yarmouth County Solid Waste Park- C&D Cell Construction
Federal contribution
$136,140
Federal share33%
of $408.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20122013201420152016
Built
Approved 4.6 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Yarmouth
- Construction start
- Oct 24, 2011(actual)
- Construction end
- Jun 15, 2012(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2011
- Construction end2 weeks earlyforecast Jun 30, 2012