New Sewer Treatment Plant
Bishop's Falls, Newfoundland and Labrador
Federal contribution
$4.4M
$4,396,460
Federal share33%
of $13.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Bishop's Falls
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Mar 15, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast May 30, 2010
- Construction end11 months lateforecast Mar 31, 2016