New Sewer Treatment Plant

Bishop's Falls, Newfoundland and Labrador

completeWastewaterCC
Federal contribution
$4.4M
$4,396,460
Federal share33%

of $13.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Bishop's Falls
Construction start
Oct 4, 2010(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 30, 2010
  • Construction end11 months lateforecast Mar 31, 2016

Also in Bishop's Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26659 in the federal list. How to read these figures.