Hampton's Hill Water Tower Replacement

Bishop's Falls, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$429,741
Federal share50%

of $859.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bishop’s Falls
Construction start
May 1, 2018(actual)
Construction end
Dec 19, 2019(actual)

Against the original forecast

  • Construction end3 months lateforecast Sep 30, 2019