Greenridge Road Waterline Upgrade

Bishop's Falls, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$176,958
Federal share37%

of $473.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Bishop’s Falls
Construction start
Aug 29, 2023(actual)
Construction end
Oct 20, 2023(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Dec 15, 2023