Back to projects

Lift Station Upgrades and Installing Sanitary Services

Bishop's Falls, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$286,389
Federal share44%

of $647.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bishop’s Falls
Construction start
Oct 10, 2016(actual)
Construction end
Mar 11, 2020(actual)

Against the original forecast

  • Construction end4 months lateforecast Nov 1, 2019

Also in Bishop's Falls