Back to projects

Turners Road Waterline and Sanitary Sewer Upgrades

Bishop's Falls, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$141,894
Federal share40%

of $354.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
20242025
Built

Approved 2 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Bishop’s Falls
Construction start
Jul 7, 2025(actual)
Construction end
Sep 8, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 15, 2025
  • Construction end2 months earlyforecast Nov 13, 2025

Also in Bishop's Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67296 in the federal list. How to read these figures.