Turners Road Waterline and Sanitary Sewer Upgrades
Bishop's Falls, Newfoundland and Labrador
Federal contribution
$141,894
Federal share40%
of $354.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
20242025
Built
Approved 2 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Bishops Falls
- Construction start
- Jul 7, 2025(actual)
- Construction end
- Sep 8, 2025(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 15, 2025
- Construction end2 months earlyforecast Nov 13, 2025