Back to projects

Curb Storm Sewer & Sidewalk, Fourth Avenue

Pasadena, Newfoundland and Labrador

completeWastewaterCC Top Up
Federal contribution
$248,061
Federal share31%

of $788.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Pasadena
Construction start
May 18, 2010(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 30, 2009
  • Construction end6 months lateforecast Feb 28, 2010

Also in Pasadena

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26707 in the federal list. How to read these figures.