Curb Storm Sewer & Sidewalk, Fourth Avenue
Pasadena, Newfoundland and Labrador
Federal contribution
$248,061
Federal share31%
of $788.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Pasadena
- Construction start
- May 18, 2010(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 30, 2009
- Construction end6 months lateforecast Feb 28, 2010
Also in Pasadena
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26707 in the federal list. How to read these figures.