Lift Station Upgrades - Five Lift Stations

Pasadena, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$725,921
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Pasadena
Construction start
Aug 18, 2018(actual)
Construction end
Nov 30, 2019(actual)

Against the original forecast

  • Construction start12 months lateforecast Aug 15, 2017